New Build Education
Hounslow Primary
Project Scope: First & Second fix carpentry
Contract size: £600K
Programme: 5 Weeks
Client:
Project summary
Hounslow Town primary school is Britain's second largest primary school with 3 floors and facilities for over 1,200 pupils. The contract was secured for all first and second fix carpentry works which included pre-hung safe hinge fire door sets, bespoke reception desk, toilet cubicle systems and bespoke glazed seating areas. DPT had a presence on site from the early stage to carry out first fix roof works and vanity frameworks, with a tight deadline looming the door installation period became very tight and it was all hands on deck to be ready for handover for the new school year.