WARWICK ACADEMY
Project Type:
New Build School
Scope of Works:
First & Second fix Carpentry & Acoustic flooring
Contract Size:
£1.2m
Programme:
36 weeks
Client:

Wariwck Academy is a part of a St Edwards development to transform the local area of kensington with over 1,000 homes including affordable housing. DPT's scope of works for this contract included all first and second fix carpentry work within the school including fire doors and special acoustic flooring. This project was different in the way that it was a timber frame construction by others and DPT were required to install joinery elements within the parameters of the different tolerances produced by a timber frame constriction. The project was delayed by 5 months by the time it was ready for second fix carpentry works, and the project still handed over in time.