HOUNSLOW PRIMARY

Project Type: 

New Build Education

Scope of Works: 

First & Second fix carpentry

Contract Size: 

£600k

Programme: 

5 weeks

Client: 

Hounslow Town primary school is Britain's second largest primary school with 3 floors and facilities for over 1,200 pupils. The contract was secured for all first and second fix carpentry works which included pre-hung safe hinge fire door sets, bespoke reception desk, toilet cubicle systems and bespoke glazed seating areas. DPT had a presence on site from the early stage to carry out first fix roof works and vanity frameworks, with a tight deadline looming the door installation period became very tight and it was all hands on deck to be ready for handover for the new school year.